Latest update for Oak Brook Rd Road Construction Project -- Salt Creek Bridge:
The installation of concrete median curbs are complete. Traffic configuration remains with only outer lanes open to accommodate the cleanup and restoration work. All lanes should be open early next week.
Latest update for Brook Forest Resurfacing Project:
All paving is complete. Restoration, cleanup and the completion of punch list items continues.